References Zuk-O-Pur LF : Installation of individual treatment plant with fixed bed biomass outside Belgium

Country / Location(*) Size in PE (**) Type of tank Year of commissioning

GERMANY

50 PE max (DIN4261, §2)
7 installations. Länder Brandebourg, Mecklembourg and Saxe. 4 to 50 Precast concrete tanks 1995
18 installations. Länder Brandebourg, Mecklembourg and Saxe. 4 to 50 Precast concrete tanks 1996
26 installations. Länder Brandebourg, Mecklembourg and Saxe. 4 to 50 Precast concrete tanks 1997
50 to 500 EH (ATV 122)
Basse-Saxe (German army) 100 Rectangular concrete tank 1995
Gosswitz (Saxe) 100 Rectangular concrete tank 1996
Dobberschütz (Saxe) 100 Container 1996
Lugau (Saxe) (Hospital) 100 Container 1997
Schwaan (Mecklembourg) 100 Container 1997
Zeuthen (Berlin) 120 Refurbishing existing tanks 1994
Wandlitz (Berlin) 144 Concrete tanks 1996
Seilershof (Brandebourg) 150 Rectangular concrete tank 1997
Herongen (Nordrhein-Westphalie) (Holiday resort) 160 Container 1998
Wünsdorf (Berlin) 200 Rectangular concrete tank 1997
Hohenleipisch (Saxe) (Senior citizen housing) 350 Container 1997
Thyrow (Brandebourg) 400 Container 1995
More than 500 PE (ATV 135)
Grebs (Brandenbourg) 1500 Precast concrete containers 1994
AUSTRALIA
Cabramurra, Snowy Mountains (2 620 m) 3 500 Container (4 stages) End 2002
CHILE
7 installations with local partner 4 to 30 Polyester tanks Since 1996
NEW ZELAND
5 installations with local partner 4 to 30 Concrete tanks Since 1997
Gesbourne (Holiday resort) 250 Concrete tanks 1999
Kiwi Ltd - Stratford (Dairy industry) 6 500 m3/day Concrete tanks 2000
Base Scott, Antarctica 122 Container End 2002
GREECE
Corfou 60 Polyethylene container 1997
Edessa (Fruits processing: peache...) 2 500 Concrete tanks 1999
PORTUGAL
Tor (Algarve) 400 Rectangular concrete tank 1995

(*) In Germany, DIN or ATV norms can be used to guarantee European discharge norms (BOD < 25 mg/l, COD < 125 mg/l and suspended matters < 35 mg/l) after treatment of waste water.

(**) PE = Population Equivalent. In Belgium, the first figure corresponds to the pollutant load that guarantees the European Norms (application of German rules of calculation); the second figure corresponds to the pollutant load that guarantees the Wallonia or Flanders norms (depending on the region).

This list is not compete and confidential. Clients can't be contacted before agreement and intervention of Zuko. It includes installations by Zuko and by subcontractors.

In every case, Zuko has modified the existing sewerage network in order to allow a rational functioning of the treatment system. Preliminary design for sewerage has always been done by Zuko.

How can we help you? Contact us!